Mybster 4 132/33kV GSP: grid connection queue
Mybster 4 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 40 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Causeymire 2 Wind Farm | HEADWIND DEVELOPMENT SERVICES LIMITED | Onshore wind | 40 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Latheron Primary | SSEN Distribution | 7.4 km | 0 MW | 1.1 MW |
| Dunbeath GSP | SSEN Distribution | 10.4 km | ||
| Mybster 1 GSP | SSEN Distribution | 11.3 km | ||
| Mybster 2 GSP | SSEN Distribution | 11.3 km | ||
| Wick Primary | SSEN Distribution | 18.2 km | 0 MW | 5 MW |
| Halkirk Primary | SSEN Distribution | 18.6 km | 0 MW | 0 MW |
Thinking of connecting near Mybster 4 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Mybster 3 132/33kV: 117 MW waiting
- Mybster 2 132/33kV: 86 MW waiting
- Spittal 2 400kV: 1,000 MW waiting
- Spittal 400kV: 600 MW waiting
- Spittal 132kV: 462 MW waiting