Greenburn Mixed Technology 132kV: grid connection queue
Greenburn Mixed Technology 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 63 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Jun 2028 to 30 Jun 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Greenburn Mixed Technology | REG GREENBURN LIMITED | Onshore wind | 63 | 30 Jun 2028 | High | 28 Aug 2030 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 7 Jul 2026 | Greenburn Mixed Technology | 31 Oct 2027 | 30 Jun 2028 | +8 months |
Thinking of connecting near Greenburn Mixed Technology 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.