Greenburn Mixed Technology 132kV: grid connection queue

Greenburn Mixed Technology 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 63 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Jun 2028 to 30 Jun 2028.

1project in the queue
63 MWwaiting to connect
0 MWalready connected
63 MWholding Gate 2
1date moves since 2 Jun 2026
63 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Greenburn Mixed TechnologyREG GREENBURN LIMITEDOnshore wind6330 Jun 2028High28 Aug 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
7 Jul 2026Greenburn Mixed Technology31 Oct 202730 Jun 2028+8 months

Thinking of connecting near Greenburn Mixed Technology 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.