East Claydon 400kV: grid connection queue
East Claydon 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 4,125 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 1 Oct 2026 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| East Claydon Storage | EAST CLAYDON STORAGE LIMITED | Battery storage | 500 | 1 Oct 2026 | n/a | Scoping | 1 | |
| Rosefield | Rosefield Energyfarm Limited | Solar + storage | 500 | 31 Oct 2031 | Medium | 31 Oct 2031 | Awaiting Consents | none |
| East Claydon Green Energy Centre | EAST CLAYDON GREEN NG LIMITED | Solar + storage | 1,025 | 1 Oct 2034 | Low | 1 Oct 2034 | Awaiting Consents | none |
| East Claydon Greener Grid Park | East Claydon Energy Limited | Battery storage | 650 | 30 Nov 2034 | Low | 30 Nov 2034 | Scoping | 1 |
| East Claydon High Impact Green Energy Hub (HIGEH) 1 | EAST CLAYDON STORAGE LIMITED | Mixed and other | 1,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| Alderton PV & BESS Station | BNRG ALBION LIMITED | Solar + storage | 450 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | East Claydon High Impact Green Energy Hub (HIGEH) 1 | 31 Oct 2034 | 6 Dec 2036 | +25 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bicester North Primary | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| Bicester North BSP | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| Cottisford Primary | SSEN Distribution | 4.4 km | 0 MW | 0 MW |
| Bicester Primary | SSEN Distribution | 5.1 km | 0 MW | 0 MW |
| Upper Heyford Primary | SSEN Distribution | 5.8 km | 0 MW | 0 MW |
| Arncott Primary | SSEN Distribution | 9.5 km | 0 MW | 0 MW |
Thinking of connecting near East Claydon 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fawley: 150 MW waiting
- Cowley 400kV: 1,157 MW waiting
- Botley West 400kV: 1,280 MW waiting
- Botley 400kV: 800 MW waiting
- Farmoor 400kV: 840 MW waiting