Fawley: grid connection queue
Fawley GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 150 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 24 Oct 2036 to 24 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Manor Farm Solar Park | CSE42 LIMITED | Solar + storage | 150 | 24 Oct 2036 | Low | 24 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| East Claydon GSP | SSEN Distribution | 8.4 km | ||
| Cottisford Primary | SSEN Distribution | 12.9 km | 0 MW | 0 MW |
| Bicester North BSP | SSEN Distribution | 15.5 km | 0 MW | 0 MW |
| Bicester North Primary | SSEN Distribution | 15.5 km | 0 MW | 0 MW |
| Waddesdon Primary 11kV | UK Power Networks | 16.1 km | 10 MW | -3.2 MW |
| Bicester Primary | SSEN Distribution | 17.7 km | 0 MW | 0 MW |
Thinking of connecting near Fawley?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- East Claydon 400kV: 4,125 MW waiting
- Chiltern Connection Node C 132kV: 150 MW waiting
- Chiltern Connection Node A 400kV: 750 MW waiting
- LAVENDON 400KV SUBSTATION: 1,000 MW waiting
- Sundon 400kV: 1,150 MW waiting