Northern Shetland 400kV: grid connection queue

Northern Shetland 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 2,300 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

2projects in the queue
2,300 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
ARVEN OFFSHORE WIND FARMARVEN OFFSHORE WIND FARM LIMITEDOffshore wind1,80031 Oct 2033Low31 Oct 2033Scopingnone
Sealtainn Offshore Wind FarmShetland Offshore Wind LimitedOffshore wind50031 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Firth PrimarySSEN Distribution5.9 km0 MW0 MW
Mid Yell PrimarySSEN Distribution11.9 km0 MW0 MW
Brae PrimarySSEN Distribution14.3 km0 MW0 MW
Voe PrimarySSEN Distribution17.3 km0 MW0 MW

Thinking of connecting near Northern Shetland 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points