Beaw Field 132/33kV: grid connection queue
Beaw Field 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 102 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Beaw Field Wind Farm | BEAW FIELD SHETLAND LIMITED | Onshore wind | 102 | 29 Oct 2032 | Low | 29 Oct 2032 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Firth Primary | SSEN Distribution | 9.7 km | 0 MW | 0 MW |
| Mid Yell Primary | SSEN Distribution | 12.0 km | 0 MW | 0 MW |
| Brae Primary | SSEN Distribution | 19.3 km | 0 MW | 0 MW |
| Gutcher Primary | SSEN Distribution | 19.8 km | 0 MW | 0 MW |
| Voe Primary | SSEN Distribution | 19.9 km | 0 MW | 0 MW |
Thinking of connecting near Beaw Field 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Northern Shetland 400kV: 2,300 MW waiting
- Energy Isles 132kV: 120 MW waiting
- Mossy Hill 132kV: 40 MW waiting