Mossy Hill 132kV: grid connection queue

Mossy Hill 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 40 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Jun 2029 to 29 Jun 2029.

1project in the queue
40 MWwaiting to connect
0 MWalready connected
40 MWholding Gate 2
1date moves since 2 Jun 2026
40 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Mossy Hill Wind FarmMOSSY HILL SHETLAND LIMITEDOnshore wind4029 Jun 2029High16 May 2031Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
3 Nov 2026Mossy Hill Wind Farm30 Nov 202829 Jun 2029+7 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Scalloway PrimarySSEN Distribution2.2 km0 MW0 MW
Lerwick PrimarySSEN Distribution3.7 km0 MW6.2 MW
Shetland / GremistaSSEN Distribution3.8 km
Sandwick PrimarySSEN Distribution14.9 km0 MW0 MW
Tumblin PrimarySSEN Distribution15.9 km0 MW0 MW

Thinking of connecting near Mossy Hill 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points