EA2A and EA2B 275/66kV Offshore Platform: grid connection queue
EA2A and EA2B 275/66kV Offshore Platform · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 880 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Mar 2028 to 31 Mar 2028.
1project in the queue
880 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
880 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| East Anglia Two | EAST ANGLIA TWO LIMITED | Offshore wind | 880 | 31 Mar 2028 | High | 15 Apr 2030 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near EA2A and EA2B 275/66kV Offshore Platform?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.