HIGH MATHERNOCK 132KV SUBSTATION: grid connection queue

HIGH MATHERNOCK 132KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 334 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 17 Oct 2029 to 17 Oct 2029.

1project in the queue
334 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
High Mathernock Battery StorageHarmony HM LimitedBattery storage33417 Oct 2029Medium17 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near HIGH MATHERNOCK 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.