Finstown: grid connection queue
Finstown GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 16 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 6 Apr 2029 to 6 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Costa Head | COSTA HEAD WIND FARM LIMITED | Onshore wind | 16 | 6 Apr 2029 | High | 21 Feb 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stromness Primary | SSEN Distribution | 8.8 km | 0 MW | 2.4 MW |
| Kirkwall Primary | SSEN Distribution | 10.7 km | 0 MW | 0 MW |
| Burgar Hill Primary | SSEN Distribution | 12.6 km | 0 MW | 0 MW |
| North Hoy Primary | SSEN Distribution | 13.8 km | 0 MW | 0.2 MW |
| Shapinsay Primary | SSEN Distribution | 14.6 km | 0 MW | 0 MW |
| St Mary's Primary | SSEN Distribution | 17.5 km | 0 MW | 0 MW |
Thinking of connecting near Finstown?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Finstown (Orkney): 20 MW waiting
- Hollandmey Renewable Energy Development132/33kV: 50 MW waiting
- Slickly Wind Farm 132kV: 114 MW waiting
- Pentland Floating Offshore Wind Farm 132/66kV substation: 100 MW waiting
- Thurso South 400kV: 500 MW waiting