Slickly Wind Farm 132kV: grid connection queue

Slickly Wind Farm 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 114 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 12 Dec 2029 to 12 Dec 2029.

1project in the queue
114 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
114 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Slickly Wind FarmSlickly Wind Farm LimitedOnshore wind + storage11412 Dec 2029High29 Oct 2031Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Hastigrow PrimarySSEN Distribution4.9 km0 MW0 MW
Wick PrimarySSEN Distribution15.6 km0 MW5 MW
Mount Pleasant PrimarySSEN Distribution16.6 km0 MW3.5 MW
Thurso South GSPSSEN Distribution16.9 km
Halkirk PrimarySSEN Distribution17.2 km0 MW0 MW
Mybster 2 GSPSSEN Distribution17.9 km

Thinking of connecting near Slickly Wind Farm 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points