Arnish 275kV: grid connection queue
Arnish 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 180 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stornoway Wind Farm | STORNOWAY WIND FARM LIMITED | Onshore wind | 180 | 31 Oct 2030 | High | 16 Sep 2032 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stornoway GSP | SSEN Distribution | 3.1 km | ||
| Battery Point Primary | SSEN Distribution | 4.8 km | 0 MW | 0 MW |
| Laxay Primary | SSEN Distribution | 9.5 km | 0 MW | 1.2 MW |
| Coll Primary | SSEN Distribution | 13.6 km | 0 MW | 0.5 MW |
| Callanish Primary | SSEN Distribution | 17.6 km | 0 MW | 0 MW |
| Barvas Primary | SSEN Distribution | 19.8 km | 0 MW | 0.6 MW |
Thinking of connecting near Arnish 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Arnish Lewis Hub 400kV: 1,395 MW waiting
- Stornoway: 75 MW waiting
- Muaitheabhal 132/33kV: 189 MW waiting