Arnish Lewis Hub 400kV: grid connection queue

Arnish Lewis Hub 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 1,395 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Dec 2030 to 31 Oct 2033.

2projects in the queue
1,395 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Spiorad Na Mara Offshore Wind FarmSPIORAD NA MARA LIMITEDOffshore wind90031 Dec 2030Medium31 Dec 2030Scopingnone
MagwindMAGNORA OFFSHORE WIND N3 LIMITEDOffshore wind49531 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Battery Point PrimarySSEN Distribution1.8 km0 MW0 MW
Stornoway GSPSSEN Distribution2.9 km
Coll PrimarySSEN Distribution10.9 km0 MW0.5 MW
Laxay PrimarySSEN Distribution12.5 km0 MW1.2 MW
Barvas PrimarySSEN Distribution19.6 km0 MW0.6 MW

Thinking of connecting near Arnish Lewis Hub 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points