Arnish Lewis Hub 400kV: grid connection queue
Arnish Lewis Hub 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 1,395 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Dec 2030 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Spiorad Na Mara Offshore Wind Farm | SPIORAD NA MARA LIMITED | Offshore wind | 900 | 31 Dec 2030 | Medium | 31 Dec 2030 | Scoping | none |
| Magwind | MAGNORA OFFSHORE WIND N3 LIMITED | Offshore wind | 495 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Battery Point Primary | SSEN Distribution | 1.8 km | 0 MW | 0 MW |
| Stornoway GSP | SSEN Distribution | 2.9 km | ||
| Coll Primary | SSEN Distribution | 10.9 km | 0 MW | 0.5 MW |
| Laxay Primary | SSEN Distribution | 12.5 km | 0 MW | 1.2 MW |
| Barvas Primary | SSEN Distribution | 19.6 km | 0 MW | 0.6 MW |
Thinking of connecting near Arnish Lewis Hub 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Arnish 275kV: 180 MW waiting
- Stornoway: 75 MW waiting
- Muaitheabhal 132/33kV: 189 MW waiting