Stornoway: grid connection queue
Stornoway GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 75 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 31 Oct 2030 to 31 Dec 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Battery Point BESS | Point and Sandwick Power Limited | Battery storage | 25 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | none |
| Druim Leathann BEGA | DRUIM LEATHANN WINDFARM LIMITED | Onshore wind | 50 | 31 Dec 2031 | Low | 31 Dec 2031 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Druim Leathann BEGA | 31 Mar 2027 | 31 Dec 2031 | +57 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Battery Point Primary | SSEN Distribution | 1.9 km | 0 MW | 0 MW |
| Stornoway GSP | SSEN Distribution | 3.0 km | ||
| Coll Primary | SSEN Distribution | 7.8 km | 0 MW | 0.5 MW |
| Laxay Primary | SSEN Distribution | 15.2 km | 0 MW | 1.2 MW |
| Barvas Primary | SSEN Distribution | 16.5 km | 0 MW | 0.6 MW |
Thinking of connecting near Stornoway?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Arnish Lewis Hub 400kV: 1,395 MW waiting
- Arnish 275kV: 180 MW waiting
- Muaitheabhal 132/33kV: 189 MW waiting