Stornoway: grid connection queue

Stornoway GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 75 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 31 Oct 2030 to 31 Dec 2031.

2projects in the queue
75 MWwaiting to connect
0 MWalready connected
50 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Battery Point BESSPoint and Sandwick Power LimitedBattery storage2531 Oct 2030Medium31 Oct 2030Scopingnone
Druim Leathann BEGADRUIM LEATHANN WINDFARM LIMITEDOnshore wind5031 Dec 2031Low31 Dec 2031Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
10 Nov 2026Druim Leathann BEGA31 Mar 202731 Dec 2031+57 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Battery Point PrimarySSEN Distribution1.9 km0 MW0 MW
Stornoway GSPSSEN Distribution3.0 km
Coll PrimarySSEN Distribution7.8 km0 MW0.5 MW
Laxay PrimarySSEN Distribution15.2 km0 MW1.2 MW
Barvas PrimarySSEN Distribution16.5 km0 MW0.6 MW

Thinking of connecting near Stornoway?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points