Muaitheabhal 132/33kV: grid connection queue
Muaitheabhal 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 189 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Dec 2030 to 31 Dec 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Muaitheabhal Wind Farm | UISENIS POWER LIMITED | Mixed and other | 189 | 31 Dec 2030 | Medium | 31 Dec 2030 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Laxay Primary | SSEN Distribution | 9.7 km | 0 MW | 1.2 MW |
| Maaruig Primary | SSEN Distribution | 11.9 km | 0 MW | 0 MW |
| Tarbert Primary | SSEN Distribution | 18.9 km | 0 MW | 2.3 MW |
Thinking of connecting near Muaitheabhal 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Arnish 275kV: 180 MW waiting
- Arnish Lewis Hub 400kV: 1,395 MW waiting
- Stornoway: 75 MW waiting