Chickerell-Mannington 400kV: grid connection queue
Chickerell-Mannington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 43 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2039 to 31 Oct 2039.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Frome Valley Energy Park | BIOSOUTH ENERGY LIMITED | Solar + storage | 43 | 31 Oct 2039 | Low | 31 Oct 2039 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Frome Valley Energy Park | 31 Oct 2037 | 31 Oct 2039 | +24 months |
Thinking of connecting near Chickerell-Mannington 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bishops Wood 132kV: 120 MW waiting
- Bishops Wood: 100 MW waiting
- Walham 400kV: 949 MW waiting
- Severn Connection Node B 400kV: 249 MW waiting
- Severn Connection Node A 132kV: 210 MW waiting