Chickerell-Mannington 400kV: grid connection queue

Chickerell-Mannington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 43 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2039 to 31 Oct 2039.

1project in the queue
43 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Frome Valley Energy ParkBIOSOUTH ENERGY LIMITEDSolar + storage4331 Oct 2039Low31 Oct 2039Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Frome Valley Energy Park31 Oct 203731 Oct 2039+24 months

Thinking of connecting near Chickerell-Mannington 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.