Walham 400kV: grid connection queue

Walham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 949 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 17 Nov 2033 to 17 Nov 2033.

2projects in the queue
949 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Walham 700MW BESSGPC 1154 LtdBattery storage70017 Nov 2033Low17 Nov 2033Scoping1
Walham PV & BESS SubGLOUCESTER ENERGY PARK LIMITEDSolar + storage24917 Nov 2033Low17 Nov 2033Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Walham 700MW BESS31 Oct 203817 Nov 2033-59 months

Thinking of connecting near Walham 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points