Walham 400kV: grid connection queue
Walham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 949 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 17 Nov 2033 to 17 Nov 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Walham 700MW BESS | GPC 1154 Ltd | Battery storage | 700 | 17 Nov 2033 | Low | 17 Nov 2033 | Scoping | 1 |
| Walham PV & BESS Sub | GLOUCESTER ENERGY PARK LIMITED | Solar + storage | 249 | 17 Nov 2033 | Low | 17 Nov 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Walham 700MW BESS | 31 Oct 2038 | 17 Nov 2033 | -59 months |
Thinking of connecting near Walham 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Severn Connection Node A 132kV: 210 MW waiting
- Severn Connection Node B 400kV: 249 MW waiting
- Iron Acton 275kV: 120 MW waiting
- Iron Acton 132kV: 100 MW waiting
- Severn Connection Node A 400kv: 1,338 MW waiting