Bishops Wood: grid connection queue
Bishops Wood GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Valley Farm | STARLIGHT ENERGY UK LIMITED | Battery storage | 100 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Bishops Wood?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bishops Wood 132kV: 120 MW waiting
- Chickerell-Mannington 400kV: 43 MW waiting
- Ironbridge 400kV: 1,300 MW waiting
- Penn 275kV: 249 MW waiting
- Penn 132kV: 100 MW waiting