TINNISBURN WIND FARM 132KV SUBSTATION: grid connection queue

TINNISBURN WIND FARM 132KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 70 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
70 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
70 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Tinnisburn Wind FarmBAYWA R.E. UK LIMITEDOnshore wind + storage7031 Oct 2031High16 Sep 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near TINNISBURN WIND FARM 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.