Derbyshire Connection Node B 400kV: grid connection queue

Derbyshire Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,090 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.

3projects in the queue
1,090 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lower Pool Energy ParkRenewable Energy Systems LimitedSolar + storage60030 Oct 2037Low30 Oct 2037Scoping1
Camp FarmCHINT SOLAR UK MANAGEMENT LTDBattery storage25030 Oct 2037Low30 Oct 2037Scoping1
Lightsource Enderby PV+BESSLightsource Renewable UK Development LimitedSolar + storage24030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
21 Jul 2026Lower Pool Energy Park31 Oct 203030 Oct 2037+84 months

Thinking of connecting near Derbyshire Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points