CRAIGHEAD WIND FARM 132kV SUBSTATION: grid connection queue
CRAIGHEAD WIND FARM 132kV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 77 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Craighead Wind Farm | GALILEO 02 LIMITED | Onshore wind | 77 | 29 Oct 2032 | Low | 29 Oct 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Craighead Wind Farm | 31 Oct 2031 | 29 Oct 2032 | +12 months |
| 13 Oct 2026 | Craighead Wind Farm | 29 Oct 2032 | 31 Oct 2031 | -12 months |
Thinking of connecting near CRAIGHEAD WIND FARM 132kV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.