CRAIGHEAD WIND FARM 132kV SUBSTATION: grid connection queue

CRAIGHEAD WIND FARM 132kV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 77 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.

1project in the queue
77 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Craighead Wind FarmGALILEO 02 LIMITEDOnshore wind7729 Oct 2032Low29 Oct 2032Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Craighead Wind Farm31 Oct 203129 Oct 2032+12 months
13 Oct 2026Craighead Wind Farm29 Oct 203231 Oct 2031-12 months

Thinking of connecting near CRAIGHEAD WIND FARM 132kV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.