Milligansbush Battery Storage 132kV: grid connection queue

Milligansbush Battery Storage 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 25 Mar 2031 to 25 Mar 2031.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Milligansbush Battery StorageMilligansbush Battery Storage LtdBattery storage20025 Mar 2031Medium25 Mar 2031Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Milligansbush Battery Storage30 Oct 203625 Mar 2031-67 months

Thinking of connecting near Milligansbush Battery Storage 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.