Milligansbush Battery Storage 132kV: grid connection queue
Milligansbush Battery Storage 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 25 Mar 2031 to 25 Mar 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Milligansbush Battery Storage | Milligansbush Battery Storage Ltd | Battery storage | 200 | 25 Mar 2031 | Medium | 25 Mar 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Milligansbush Battery Storage | 30 Oct 2036 | 25 Mar 2031 | -67 months |
Thinking of connecting near Milligansbush Battery Storage 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.