Cellarhead 132kV: grid connection queue
Cellarhead 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 280 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cellarhead Home Farm | CELLARHEAD BESS LTD | Battery storage | 280 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Church Lawton T1 | SP Energy Networks | 14.7 km | 3.8 MW | |
| Twyfords T1 | SP Energy Networks | 14.7 km | 8.3 MW | 3.1 MW |
| Radway Green Gt1 | SP Energy Networks | 15.9 km | 157 MW | -3.2 MW |
| Radway Green Gt2 | SP Energy Networks | 15.9 km | 157 MW | -3.2 MW |
| Radway Green T1 | SP Energy Networks | 15.9 km | -2.3 MW | |
| Weston T1 | SP Energy Networks | 18.2 km | 12 MW | 2.7 MW |
Thinking of connecting near Cellarhead 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cellarhead 400kV: 1,400 MW waiting
- Staffordshire Connection Node A 400kV: 2,760 MW waiting
- Staffordshire Connection Node C 400Kv: 200 MW waiting
- Staffordshire Connection Node D 132kV: 300 MW waiting
- Staffordshire Connection Node B 132kV: 250 MW waiting