Cellarhead 400kV: grid connection queue

Cellarhead 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,400 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 13 Sep 2028 to 30 Nov 2037.

4projects in the queue
1,400 MWwaiting to connect
0 MWalready connected
300 MWholding Gate 2
3date moves since 2 Jun 2026
700 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Cellarhead 400kV Energy StorageC & S ENERGY LIMITEDBattery storage30013 Sep 2028High13 Sep 2030Under Construction/Commissioning2
Cellarhead Green Energy CentreS & C ENERGY LIMITEDSolar + storage40030 Oct 2028High30 Oct 2030Awaiting Consentsnone
CellarheadENSO GREEN HOLDINGS X LIMITEDSolar + storage40031 Oct 2033Low31 Oct 2033Scoping1
Thorney EdgeARL Energy Development LimitedBattery storage30030 Nov 2037Low30 Nov 2037Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Cellarhead31 Oct 203131 Oct 2033+24 months
13 Oct 2026Cellarhead31 Oct 203331 Oct 2031-24 months
6 Oct 2026Cellarhead 400kV Energy Storage16 Jul 202713 Sep 2028+14 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Church Lawton T1SP Energy Networks14.7 km3.8 MW
Twyfords T1SP Energy Networks14.7 km8.3 MW3.1 MW
Radway Green Gt1SP Energy Networks15.9 km157 MW-3.2 MW
Radway Green Gt2SP Energy Networks15.9 km157 MW-3.2 MW
Radway Green T1SP Energy Networks15.9 km-2.3 MW
Weston T1SP Energy Networks18.2 km12 MW2.7 MW

Thinking of connecting near Cellarhead 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.