Cellarhead 400kV: grid connection queue
Cellarhead 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,400 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 13 Sep 2028 to 30 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cellarhead 400kV Energy Storage | C & S ENERGY LIMITED | Battery storage | 300 | 13 Sep 2028 | High | 13 Sep 2030 | Under Construction/Commissioning | 2 |
| Cellarhead Green Energy Centre | S & C ENERGY LIMITED | Solar + storage | 400 | 30 Oct 2028 | High | 30 Oct 2030 | Awaiting Consents | none |
| Cellarhead | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| Thorney Edge | ARL Energy Development Limited | Battery storage | 300 | 30 Nov 2037 | Low | 30 Nov 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 2 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Cellarhead | 31 Oct 2031 | 31 Oct 2033 | +24 months |
| 13 Oct 2026 | Cellarhead | 31 Oct 2033 | 31 Oct 2031 | -24 months |
| 6 Oct 2026 | Cellarhead 400kV Energy Storage | 16 Jul 2027 | 13 Sep 2028 | +14 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Church Lawton T1 | SP Energy Networks | 14.7 km | 3.8 MW | |
| Twyfords T1 | SP Energy Networks | 14.7 km | 8.3 MW | 3.1 MW |
| Radway Green Gt1 | SP Energy Networks | 15.9 km | 157 MW | -3.2 MW |
| Radway Green Gt2 | SP Energy Networks | 15.9 km | 157 MW | -3.2 MW |
| Radway Green T1 | SP Energy Networks | 15.9 km | -2.3 MW | |
| Weston T1 | SP Energy Networks | 18.2 km | 12 MW | 2.7 MW |
Thinking of connecting near Cellarhead 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cellarhead 132kV: 280 MW waiting
- Staffordshire Connection Node A 400kV: 2,760 MW waiting
- Staffordshire Connection Node C 400Kv: 200 MW waiting
- Staffordshire Connection Node D 132kV: 300 MW waiting
- Staffordshire Connection Node B 132kV: 250 MW waiting