Kinardochy Substation 400/275kV: grid connection queue
Kinardochy Substation 400/275kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.
1project in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Field Kinardochy BESS | Field Kinardochy Ltd | Battery storage | 400 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Kinardochy Substation 400/275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.