GALLOS 66KV OFFSHORE SUBSTATION: grid connection queue
GALLOS 66KV OFFSHORE SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 2,000 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 6 Dec 2036 to 6 Dec 2036.
1project in the queue
2,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Gallos | Corio Generation Limited | Offshore wind | 2,000 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near GALLOS 66KV OFFSHORE SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.