Rothienorman 400kV: grid connection queue
Rothienorman 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jul 2029 to 30 Jul 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rothienorman Battery | BLACKFORD RENEWABLES LTD | Battery storage | 500 | 30 Jul 2029 | Medium | 30 Jul 2029 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Rothienorman Battery | 31 Oct 2033 | 30 Jul 2029 | -51 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Rothienorman GSP | SSEN Distribution | 3.1 km | ||
| Fyvie Primary | SSEN Distribution | 4.9 km | 0 MW | 0 MW |
| Insch Primary | SSEN Distribution | 11.5 km | 0 MW | 0.5 MW |
| Oldmeldrum Primary | SSEN Distribution | 12.7 km | 0 MW | 0 MW |
| Methlick Primary | SSEN Distribution | 13.2 km | 0 MW | 0 MW |
| Inverurie Primary | SSEN Distribution | 14.5 km | 0 MW | 12 MW |
Thinking of connecting near Rothienorman 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rothienorman 2 400/33kV: 65 MW waiting
- Rothienorman 400/33kV: 50 MW waiting
- Greens 400kV: 3,500 MW waiting
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting