Rothienorman 2 400/33kV: grid connection queue
Rothienorman 2 400/33kV GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 65 MW are waiting to connect here (largest by capacity: battery storage, onshore wind). Contracted dates run from 31 Oct 2024 to 16 Jul 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Overhill BESS | PULSE CLEAN ENERGY SPV WATT LIMITED | Battery storage | 50 | 31 Oct 2024 | n/a | Consents Approved | none | |
| Stoneyfield | WIND 2 LIMITED | Onshore wind | 15 | 16 Jul 2032 | Low | 16 Jul 2032 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 17 Nov 2026 | Stoneyfield | 30 Sep 2030 | 16 Jul 2032 | +22 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Rothienorman GSP | SSEN Distribution | 3.1 km | ||
| Fyvie Primary | SSEN Distribution | 4.9 km | 0 MW | 0 MW |
| Insch Primary | SSEN Distribution | 11.5 km | 0 MW | 0.5 MW |
| Oldmeldrum Primary | SSEN Distribution | 12.7 km | 0 MW | 0 MW |
| Methlick Primary | SSEN Distribution | 13.2 km | 0 MW | 0 MW |
| Inverurie Primary | SSEN Distribution | 14.5 km | 0 MW | 12 MW |
Thinking of connecting near Rothienorman 2 400/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rothienorman 400kV: 500 MW waiting
- Rothienorman 400/33kV: 50 MW waiting
- Greens 400kV: 3,500 MW waiting
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting