Garvary 132kV: grid connection queue

Garvary 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 144 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 5 Aug 2029 to 5 Aug 2029.

1project in the queue
144 MWwaiting to connect
0 MWalready connected
144 MWholding Gate 2
1date moves since 2 Jun 2026
144 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Garvary Wind FarmGARVARY WIND FARM LIMITEDOnshore wind1445 Aug 2029High22 Jun 2031Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
10 Nov 2026Garvary Wind Farm30 Jun 20285 Aug 2029+13 months

Thinking of connecting near Garvary 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.