Garvary 132kV: grid connection queue
Garvary 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 144 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 5 Aug 2029 to 5 Aug 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Garvary Wind Farm | GARVARY WIND FARM LIMITED | Onshore wind | 144 | 5 Aug 2029 | High | 22 Jun 2031 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Garvary Wind Farm | 30 Jun 2028 | 5 Aug 2029 | +13 months |
Thinking of connecting near Garvary 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.