Shin 1: grid connection queue

Shin 1 GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

3 projects with 164 MW are waiting to connect here (largest by capacity: onshore wind + storage, mixed and other). Contracted dates run from 30 Jun 2031 to 31 Oct 2032.

3projects in the queue
164 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Allt an Tuir Renewable Energy ParkALLT AN TUIR RENEWABLE ENERGY PARK LIMITEDMixed and other5030 Jun 2031Medium30 Jun 2031Scopingnone
Strath Oykel Wind FarmENERGYFARM STRATH OYKEL LLPOnshore wind + storage7431 Oct 2032Low31 Oct 2032Awaiting Consentsnone
Meall Buidhe Wind FarmMUIRDEN ENERGY LLPOnshore wind4031 Oct 2032Low31 Oct 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Gledfield PrimarySSEN Distribution7.3 km0 MW1.7 MW
Shin GSPSSEN Distribution8.4 km
Shin PrimarySSEN Distribution8.4 km0 MW2.5 MW
Conon Falls PrimarySSEN Distribution8.4 km0 MW0 MW
Lairg GSPSSEN Distribution17.4 km
Lairg PrimarySSEN Distribution17.4 km0 MW1.6 MW

Thinking of connecting near Shin 1?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points