BRORA 132/33KV GRID SUPPLY POINT SUBSTATION: grid connection queue
BRORA 132/33KV GRID SUPPLY POINT SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Crakaig Wind Energy Hub | CRAKAIG WIND ENERGY HUB LIMITED | Onshore wind + storage | 60 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Brora GSP | SSEN Distribution | 7.7 km | ||
| Brora Primary | SSEN Distribution | 8.7 km | 0 MW | 4 MW |
| Golspie Primary | SSEN Distribution | 13.1 km | 0 MW | 0.8 MW |
| Helmsdale Primary | SSEN Distribution | 15.1 km | 0 MW | 0.3 MW |
| Torboll Primary | SSEN Distribution | 16.9 km | 0 MW | 0.1 MW |
| Tressady Primary | SSEN Distribution | 19.2 km | 0 MW | 0.2 MW |
Thinking of connecting near BRORA 132/33KV GRID SUPPLY POINT SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Brora: 50 MW waiting
- Kilbraur Wind Farm: 79 MW waiting
- Chleansaid Wind Farm 132kV: 96 MW waiting
- Coille Linne 132kV: 113 MW waiting
- Dalchork 132kV: 200 MW waiting