Osbaldwick 400kV: grid connection queue
Osbaldwick 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 307 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 8 Jun 2027 to 30 Aug 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Monets Garden | MONETS GARDEN BATTERY LTD | Battery storage | 57 | 8 Jun 2027 | High | 7 Jun 2029 | Consents Approved | 2 |
| Osbaldwick PV & BESS Sub | YORK ENERGY PARK LIMITED | Solar + storage | 250 | 30 Aug 2033 | Low | 30 Aug 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 21 Jul 2026 | Monets Garden | 30 Oct 2024 | 8 Jun 2027 | +31 months |
Thinking of connecting near Osbaldwick 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Thormanby 400kV: 600 MW waiting
- North Humber Connection Node C 400kV: 200 MW waiting
- Thornton 400kV: 1,790 MW waiting
- Thornton B 400kV: 250 MW waiting
- Lackenby 400kV: 1,800 MW waiting