Thornton 400kV: grid connection queue

Thornton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,790 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 29 Oct 2027 to 28 Oct 2033.

4projects in the queue
1,790 MWwaiting to connect
100 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
830 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Thornton FacilityBALWEN LIMITEDSolar + storage83029 Oct 2027High28 Oct 2029Consents Approvednone
ThorntonIGP SOLAR 19 LIMITEDSolar + storage50031 Oct 2031Medium31 Oct 2031Scopingnone
Derwent Solar PV ArrayANESCO LIMITEDSolar16031 May 2032Low31 May 2032Scopingnone
Elmya Melbourne BESSELMYA RPC UK MELBOURNE LIMITEDBattery storage30028 Oct 2033Low28 Oct 2033Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Thornton 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points