Thornton 400kV: grid connection queue
Thornton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,790 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 29 Oct 2027 to 28 Oct 2033.
4projects in the queue
1,790 MWwaiting to connect
100 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
830 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Thornton Facility | BALWEN LIMITED | Solar + storage | 830 | 29 Oct 2027 | High | 28 Oct 2029 | Consents Approved | none |
| Thornton | IGP SOLAR 19 LIMITED | Solar + storage | 500 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
| Derwent Solar PV Array | ANESCO LIMITED | Solar | 160 | 31 May 2032 | Low | 31 May 2032 | Scoping | none |
| Elmya Melbourne BESS | ELMYA RPC UK MELBOURNE LIMITED | Battery storage | 300 | 28 Oct 2033 | Low | 28 Oct 2033 | Awaiting Consents | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Thornton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Thornton B 400kV: 250 MW waiting
- North Humber Connection Node C 400kV: 200 MW waiting
- Creyke Beck 400kV: 7,578 MW waiting
- Creyke Beck: 470 MW waiting
- Creyke Beck 132kV: 100 MW waiting