Abernethy 2: grid connection queue
Abernethy 2 GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 20 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Shire End Solar Farm | QAIR SCOTLAND LIMITED | Solar | 20 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bridge of Earn Primary | SSEN Distribution | 2.8 km | 0 MW | 11 MW |
| Abernethy Primary | SSEN Distribution | 7.0 km | 0 MW | 1.1 MW |
| Abernethy GSP | SSEN Distribution | 7.0 km | ||
| Harbour Primary | SSEN Distribution | 7.2 km | 0 MW | 11 MW |
| Thimblerow Primary | SSEN Distribution | 9.0 km | 0 MW | 0 MW |
| Forteviot Primary | SSEN Distribution | 9.5 km | 0 MW | 4.2 MW |
Thinking of connecting near Abernethy 2?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Abernethy 132kV: 50 MW waiting
- OCHILL BESS 132KV SUBSTATION: 50 MW waiting
- Conland: 400 MW waiting
- Leslie 200MW BESS 275kV: 200 MW waiting
- Glenrothes 275/33kV: 46 MW waiting