Conland: grid connection queue
Conland Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 400 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2031 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glenrothes Hybrid BESS & Solar PV | TAGENERGY DEVELOPMENT UK LIMITED | Solar + storage | 200 | 30 Oct 2031 | Medium | 30 Oct 2031 | Scoping | 1 |
| Pitkevy BESS | HARMONY ENERGY LIMITED | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Glenrothes Hybrid BESS & Solar PV | 30 Apr 2031 | 30 Oct 2031 | +6 months |
| 13 Oct 2026 | Glenrothes Hybrid BESS & Solar PV | 30 Oct 2031 | 30 Apr 2031 | -6 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Collydene | SP Energy Networks | 1.9 km | 19 MW | |
| Glenwood | SP Energy Networks | 2.4 km | 19 MW | 11 MW |
| Queensway | SP Energy Networks | 3.8 km | 21 MW | 13 MW |
| Warout Road | SP Energy Networks | 4.1 km | 2.5 MW | |
| Southfield | SP Energy Networks | 4.4 km | 20 MW | 15 MW |
| Pitteuchar | SP Energy Networks | 5.3 km | 12 MW |
Thinking of connecting near Conland?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Leslie 200MW BESS 275kV: 200 MW waiting
- Glenrothes 275/33kV: 46 MW waiting
- Kirkcaldy BESS 132kV: 100 MW waiting
- Smeaton 400/275kV: 300 MW waiting
- Smeaton 400kV: 228 MW waiting