Penwortham 400kV: grid connection queue
Penwortham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 2,694 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Penwortham BESS | PENWORTHAM (BES) LTD | Battery storage | 57 | 30 Oct 2028 | High | 30 Oct 2030 | Consents Approved | 2 |
| Morecambe Offshore Wind Farm | MORECAMBE OFFSHORE WINDFARM LTD | Offshore wind | 480 | 30 Jun 2029 | Medium | 30 Jun 2029 | Scoping | none |
| Morgan Offshore Wind Farm | Morgan Offshore Wind Limited | Offshore wind | 1,500 | 30 Nov 2029 | Medium | 30 Nov 2029 | Scoping | none |
| Penwortham BESS | CSE28 LIMITED | Battery storage | 57 | 1 Jun 2031 | Medium | 1 Jun 2031 | Scoping | 1 |
| Penwortham Green Energy Centre | Penwortham NG Limited | Solar + storage | 600 | 30 Oct 2035 | Low | 30 Oct 2035 | Awaiting Consents | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Penwortham BESS | 30 Oct 2027 | 30 Oct 2028 | +12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 400218 | Electricity North West | 2.2 km | 11 MW | 10 MW |
| Primary substation 400208 | Electricity North West | 2.3 km | 11 MW | 6.8 MW |
| Primary substation 400402 | Electricity North West | 2.5 km | 11 MW | 0 MW |
| Primary substation 400406 | Electricity North West | 2.6 km | 11 MW | 8.1 MW |
| Primary substation 400419 | Electricity North West | 3.8 km | 11 MW | 5.3 MW |
| Primary substation 400412 | Electricity North West | 4.0 km | 11 MW | 6.9 MW |
Thinking of connecting near Penwortham 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lancashire Connection Node B 400kV: 1,200 MW waiting
- Kirkby 275kV: 400 MW waiting
- Kirkby 275/33kV: 114 MW waiting
- Kearsley 275kV: 450 MW waiting
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION: 1,260 MW waiting