Oakley 400kV: grid connection queue
Oakley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 600 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Nov 2038 to 1 Nov 2038.
1project in the queue
600 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Oakley | SSE DE SOLAR HOLDCO LIMITED | Solar + storage | 600 | 1 Nov 2038 | Low | 1 Nov 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Oakley 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.