Peterhead 132KV: grid connection queue
Peterhead 132KV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Mar 2030 to 31 Mar 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Salamander Offshore Wind Farm | SALAMANDER WIND PROJECT COMPANY LIMITED | Offshore wind | 200 | 31 Mar 2030 | Medium | 31 Mar 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Boddam Primary | SSEN Distribution | 0.7 km | 7.3 MW | 0 MW |
| Peterhead Shell GSP | SSEN Distribution | 0.8 km | ||
| Peterhead North Street Primary | SSEN Distribution | 3.5 km | 0 MW | 0 MW |
| Peterhead Grange GSP | SSEN Distribution | 3.6 km | ||
| Peterhead Grange Primary | SSEN Distribution | 3.6 km | 0 MW | 0 MW |
| Stoneyhill Primary | SSEN Distribution | 5.4 km | 0 MW | 3.8 MW |
Thinking of connecting near Peterhead 132KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Peterhead 275kV: 910 MW waiting
- Peterhead 2 400kV Busbar Extension: 200 MW waiting
- Peterhead Grange: 50 MW waiting
- ST FERGUS 132KV SWITCHING STATION: 100 MW waiting
- St Fergus: 100 MW waiting