Cassley: grid connection queue
Cassley GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Jul 2028 to 31 Jul 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sallachy Wind Farm | SALLACHY WIND LIMITED | Onshore wind | 50 | 31 Jul 2028 | High | 28 Sep 2030 | Awaiting Consents | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Sallachy Wind Farm | 31 Aug 2027 | 31 Jul 2028 | +11 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Rhiconich Primary | SSEN Distribution | 9.9 km | 0 MW | 2.8 MW |
Thinking of connecting near Cassley?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Creag Riabhach 132/33kV: 13 MW waiting
- Acheilidh Wind farm 132kV: 84 MW waiting
- Chleansaid Wind Farm 132kV: 96 MW waiting
- New Dounreay 400kV substation: 1,700 MW waiting
- DOUNREAY 2 275 kV SUBSTATION: 500 MW waiting