Acheilidh Wind farm 132kV: grid connection queue
Acheilidh Wind farm 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 84 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Acheilidh Wind Farm | ENERGYFARM UK ACHEILIDH LTD | Onshore wind + storage | 84 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lochinver Primary | SSEN Distribution | 3.5 km | 0 MW | 0 MW |
| Achiltibuie Primary | SSEN Distribution | 16.2 km | 0 MW | 0 MW |
Thinking of connecting near Acheilidh Wind farm 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cassley: 50 MW waiting
- Grudie Bridge: 50 MW waiting
- ACHANY EXTENSION WIND FARM 132/33KV: 81 MW waiting
- Creag Riabhach 132/33kV: 13 MW waiting
- Oykel Wind Farm 132kV: 79 MW waiting