New North East Substation 400kV: grid connection queue

New North East Substation 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

3 projects with 1,400 MW are waiting to connect here (largest by capacity: onshore wind + storage, mixed and other). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

3projects in the queue
1,400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Glenfiddich WestBORALEX LIMITEDOnshore wind + storage60031 Oct 2037Low31 Oct 2037Scoping1
Longhaven Energy Storage CentreHydrostor UK LtdMixed and other50031 Oct 2037Low31 Oct 2037Scoping1
Rattray BESS and Solar PlantGREENTECH PROJECTS HOLDING UK LIMITEDSolar + storage30031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near New North East Substation 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.