Benzene

AYR DBB 275KV SUBSTATION: grid connection queue

AYR DBB 275KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 450 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.

1project in the queue
450 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ayr FlexpowerAyr Flexpower LimitedSolar + storage45030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near AYR DBB 275KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.