Derbyshire Connection Node E 400kV: grid connection queue
Derbyshire Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 240 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
1project in the queue
240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lightsource Bagots Farm | Lightsource Renewable UK Development Limited | Onshore wind + storage | 240 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Derbyshire Connection Node E 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Derbyshire Connection Node A 400kV: 2,332 MW waiting
- Kegworth B (Derbyshire Connection Node C) 132kV: 120 MW waiting
- DERBYSHIRE CONNECTION NODE E 132 KV SUBSTATION: 480 MW waiting
- Chesterfield 400kV Substation (Not yet constructed): 657 MW waiting
- Derbyshire Connection Node G 400kV: 2,039 MW waiting