Langbank 132kV: grid connection queue
Langbank 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 29 Oct 2027 to 29 Oct 2027.
1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
50 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Langbank Solar and BESS | UK RENFREWSHIRE 1 LTD | Solar + storage | 50 | 29 Oct 2027 | High | 28 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Langbank 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.