Hartmoor 275kV: grid connection queue
Hartmoor 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 238 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2027 to 31 May 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Worset PV & BESS Park | Worcestershire Solar 1 Limited | Solar + storage | 38 | 30 Oct 2027 | High | 29 Oct 2029 | Under Construction/Commissioning | 2 |
| WORSET LANE BESS | FIELD HARTMOOR LTD | Battery storage | 200 | 31 May 2029 | Medium | 31 May 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Worset PV & BESS Park | 7 Jun 2024 | 30 Oct 2027 | +41 months |
| 28 Jul 2026 | WORSET LANE BESS | 25 Oct 2026 | 31 May 2029 | +31 months |
Thinking of connecting near Hartmoor 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hartmoor: 240 MW waiting
- Teeside Connection Node B: 3,600 MW waiting
- Saltholme 275kV: 200 MW waiting
- Wearside Connection Node D 400kV: 1,300 MW waiting
- Teeside Connection Node A 132kV: 228 MW waiting