Hartmoor 275kV: grid connection queue

Hartmoor 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 238 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2027 to 31 May 2029.

2projects in the queue
238 MWwaiting to connect
0 MWalready connected
238 MWholding Gate 2
2date moves since 2 Jun 2026
38 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Worset PV & BESS ParkWorcestershire Solar 1 LimitedSolar + storage3830 Oct 2027High29 Oct 2029Under Construction/Commissioning2
WORSET LANE BESSFIELD HARTMOOR LTDBattery storage20031 May 2029Medium31 May 2029Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
28 Jul 2026Worset PV & BESS Park7 Jun 202430 Oct 2027+41 months
28 Jul 2026WORSET LANE BESS25 Oct 202631 May 2029+31 months

Thinking of connecting near Hartmoor 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points