Tangy IV 132KV: grid connection queue

Tangy IV 132KV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 96 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2029 to 30 Apr 2029.

1project in the queue
96 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
96 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Tangy IV WFSSE Renewables Services (UK) LimitedOnshore wind9630 Apr 2029High17 Mar 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Tangy IV 132KV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.