Benzene

Bloch Energy Park 132kV: grid connection queue

Bloch Energy Park 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 126 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
126 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
126 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bloch Energy ParkRenewable Energy Systems LimitedOnshore wind + storage12631 Oct 2031High16 Sep 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Bloch Energy Park 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.