Letham 400/275kV substation: grid connection queue
Letham 400/275kV substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 300 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Jun 2032 to 30 Jun 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Grangemouth Hybrid BESS & Solar PV | TAGENERGY DEVELOPMENT UK LIMITED | Solar + storage | 300 | 30 Jun 2032 | Low | 30 Jun 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Grangemouth Hybrid BESS & Solar PV | 30 Apr 2032 | 30 Jun 2032 | +2 months |
| 13 Oct 2026 | Grangemouth Hybrid BESS & Solar PV | 30 Jun 2032 | 30 Apr 2032 | -2 months |
Thinking of connecting near Letham 400/275kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.