Dumfries North 400/132kV substation: grid connection queue
Dumfries North 400/132kV substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 43 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Balgray Wind Farm | FRED OLSEN RENEWABLES LIMITED | Onshore wind + storage | 43 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maxwellton | SP Energy Networks | 0.5 km | 13 MW | |
| Dumfries 11Kv | SP Energy Networks | 1.3 km | 27 MW | 7.1 MW |
| Lochside | SP Energy Networks | 2.5 km | 11 MW | 7.1 MW |
| Heathhall | SP Energy Networks | 3.2 km | 18 MW | 11 MW |
| Heathfield | SP Energy Networks | 3.2 km | 13 MW | |
| Cargenbridge | SP Energy Networks | 3.3 km | 23 MW | 13 MW |
Thinking of connecting near Dumfries North 400/132kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Dumfries North 400kV: 200 MW waiting
- Dumfries 132/33kV: 90 MW waiting
- Windyhill 275/132kV: 200 MW waiting
- Harestanes West Wind Farm 132/33kV: 119 MW waiting
- Wyseby Hill Energy Farm 400kV: 750 MW waiting