Blyth 400kV: grid connection queue
Blyth 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 3,200 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 30 Nov 2029 to 31 Oct 2036.
3projects in the queue
3,200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm C | BERWICK BANK C LIMITED | Offshore wind | 1,800 | 30 Nov 2029 | Medium | 30 Nov 2029 | Scoping | none |
| Icewind Blyth | KARI ENERGY LIMITED | Offshore wind | 1,000 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
| Hope Battery Storage | IBV BRINKBURN ENERGY PARK LIMITED | Battery storage | 400 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Blyth 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Blyth 275kV: 450 MW waiting
- Tynemouth 275kV: 70 MW waiting
- Stella West 400kV: 350 MW waiting
- Wearside Connection Node A 275kV: 1,100 MW waiting
- Wearside Connection Node B 400kV: 1,797 MW waiting